Perdido Project Start Up Day 4 & 5

Fuel Gas Booster from the Drive Motor Side

We are WOG (waiting on gas).  The plant is complete, the flare package is complete and we are waiting on the programming to be complete on the flare package to start moving gas to the plant.  Plent activities yesterday and today are cleaning and finishing loose ends.

Once we have gas to the plant we will start the generators up and begin tuning them as much as we can until we need to load them up.  Enercon will be in on Monday to finish the work with the switchgear and Chuck Anderson will be in Wednesday to phase and set relays.  Gulf Power will need to inspect and test their safety systems as well as their own and then we will be ready to load the generators.

Keep in touch.