Perdido LFG Plant Start Up – Day 3

2- 3520C CAT Generators - 3.2 MW in Phase 1

Plant start up shifts into getting the generators and switchgear ready.  Patten Power from Chicago is helping the LFG Tech team preping the engines.  ENERCON will be here on Monday to finish the prep for the switchgear and Chuck Anderson with LFG Tech will be in later next week to finish the “phasing” and relay settings.

If anyone has any questions, please feel free to ask.

Regards,

Barry